-COVID-19 is having some impact on the data centre market
-Drop in estimated take up in 2020 from original estimate of 197MW made in Q4, 2019, to 184MW
-That could change through H2, as markets either suffer new lock-down measures or rebound
-Development of some data centres scheduled for 2020 are being pushed to 2021
-65MW of new supply has come online during H1, mostly in Frankfurt and Amsterdam
-Absorption rates in London, Paris and Frankfurt are decreasing
-Hyperscalers are still driving demand in terms of size of deals across FLAP